Glasgow Resilience Project
Overview
Scottish Water is preparing to begin work to improve its water mains network in the south west of Glasgow by installing more than seven miles of new pipes.
The work will connect the Glasgow area’s network and the system in Ayrshire to increase resilience and protect supplies for customers and will involve the use of innovative construction materials and techniques to reduce carbon emissions and power requirements.
About one million people will benefit from the two networks being connected.
The project, the third stage in a major investment that has already delivered improvements in Ayrshire, is being delivered by our alliance partner Caledonia Water Alliance (CWA) and is expected to be completed by 2023.
Virtual Platform
To find out more about the next phase of this project, visit our virtual platform and explore the videos, information boards and maps. You can also leave a message, ask a question or provide feedback on the project.
At a Glance
- Supply Resilience
- Major Infrastructure Investment
- Delivered by Caledonia Water Alliance
- Approx completion 2023
Take a Virtual Tour
Click the link below and follow these steps to receive your unique access link by email.
- Read and agree the Data Processing Permission pop-up
- Provide your name, email address and select both “virtual attendee” and “check me in” boxes. This is essential to ensure your unique link is active when you receive it
- Check for your confirmation email, which may take a few minutes
- Click on the live link in the email to explore the virtual platform
Network Improvements
Around a million customers in Glasgow and Ayrshire will benefit from this major investment to improve the water mains network.
What We Are Doing
The new water main will be installed in the Ibrox, Mosspark, Pollok, Priesthill, Nitshill, and Parkhouse areas of Glasgow. and will run from Ibrox to a reservoir storage tank in the Parkhouse/Darnley area.
A new pumping station will be built at Ibrox which will push water to an existing pumping station in Parkhouse/Darnley for onward distribution to Ayrshire.
Four tunnels - one under the M8 motorway and the Glasgow-Ayr railway line, another under the Paisley Canal railway and White Cart Water, another under the Glasgow-Barrhead-Kilmarnock railway, and one under the Levern Water - will be constructed along the route of the new main.
There will be road crossings where the main will be installed at 15 locations including, from north to south: Edmiston Drive, Mosspark Boulevard, Corkerhill Road, Kinnell Avenue, Linthaugh Road, Braidcraft Road, Barrhead Road, Nitshill Road, Darnley Road, and Corselet Road.
It will also be installed in a number of parks, including Bellahouston Park and Househill Park.
There will be a significant amount of construction activity and while there will be some disruption in communities and for road users, we will do our very best to minimise this.
The design of the new network incorporates carbon reducing construction materials and methods including innovative self-restraining pipe. Solar panels will also offset the power demands at the new Ibrox pumping station, with the new mains using gravity to reduce power use by 60 per cent.
Why We Are Doing This
Connecting the networks will provide a two-way water supply between the Milngavie Water Treatment Works (WTW) system, which provides water for more than 700,000 people across much of the Glasgow area, and the Bradan WTW system which supplies more than 200,000 customers across much of Ayrshire. It will also benefit almost 50,000 customers in East Renfrewshire.
In the event of a disruption to water supply in either Ayrshire or Glasgow, the new system will allow millions of litres of water to be transferred in either direction, minimising the impact on customers if there is a burst main or other operational issues.
Linking our supply systems will ensure that high quality drinking water can continue to be supplied to current customers and for generations to come.
The investment in new pipelines and associated infrastructure below ground will also support the continued development above ground in communities across these areas and will enable them to continue to grow and thrive.
New Infrastructure
More than seven miles of new pipes will be installed to connect networks between Glasgow and Ayrshire.
Latest Updates
We are currently carrying out preparatory work at locations across the south side of Glasgow. This work, which is required in advance of the bird nesting season, includes tree and vegetation removal across several areas including Bellahouston Park and Househill Park, Barrhead Road, Glasgow.